Trail Report, August 23rd, 2011
Greater Snow King Area/Munger Mountain Area/Teton Pass Area
The Silver Star work on Teton Pass continues to progress: they are already below Crater Lake and moving down Old Pass Road. Heavy equipment remains on Old Pass Road during this project. To ensure public safety, temporary trail closures will be in place where machinery is working. To read the entire press release, click here.
Below you will find today’s trails and pathways report for Jackson Hole. Friends of Pathways and the Forest Service have trail crews out on the systems daily, working hard on trail maintenance and construction. Friends of Pathways also works with Jackson Hole Community Pathways and Teton County Parks and Recreation to ensure pathways are swept and safe.
Trail Report, August 1oth, 2011
Greater Snow King Area/Munger Mountain Area/Teton Pass Area
Last week the FS crew worked with a Wilderness Ventures group clearing the Dog Creek to Little Dog Creek loop.
The FOP crew worked on completing two new sections of trail: one at the bottom of Phillips Ridge, with the help of several volunteer groups, and the other a connector trail from the Pine Glades development to Sink or Swim, which trail crews are hoping to call the “Shade Monkey Trail.” This trail was made with a mini excavator that narrowed down to 3 feet wide, providing 2,244’ of shaded single track. Both of these new sections should be finished this week.
The TFR crew has finished some work on the upper Fuzzy Bunny trail including some new road gap jumps.
Crews and volunteers are working hard daily, addressing problem areas first and then moving to trail improvements as needed. Please be patient, send in your observations, and come out and help - Friday AM’s have now moved to the Teton Pass Area (meet at the Stagecoach at 8am).
Possible Old Pass Road Closures
Silver Star Communications began work this week to install fiber optic cable along the Old Pass Road. This work is park of a larger project to install approximately 100 miles of high-speed fiber optic cable to improve connectivity of broadband service across Wyoming. The work along Old Pass Road will help complete a key loop for this project. Heavy equipment will be on Old Pass Road during the project, which is expected to take about two weeks. To ensure public safety, temporary trail closures will be in place where machinery is working. To read the entire press release, click here.
Pathways Report, August 10th, 2011
Pathways should be open to use during the asphalt patching work, but users should follow instructions from work crews and pay attention to regulatory warning signs. During the sealcoating work, sections of pathway will be closed temporarily.
County Begins Work on South Park Loop Bridges, Road Closure near Melody Ranch
On August 15th, Teton County will begin construction work to replace the existing South Park Loop Road Bridge over Flat Creek near Melody Ranch. This project will require closure of the South Park Loop Road in the vicinity of Melody Ranch for the entire 4-month construction period. Concurrent with the road bridge project, the County will also begin construction of a new pathway bridge over Flat Creek adjacent to South Park Loop Road. The bridges will be operational and South Park Loop Road will re-open by mid-December. To read the complete press release, click here.
The fine folks at the Teton Freedom Riders are still getting after it! If you have the time to help them help our trails, you shouldn’t pass this opportunity:
Below you will find today’s trails and pathways report for Jackson Hole. Friends of Pathways and the Forest Service have trail crews out on the systems daily, working hard on trail maintenance and construction. Friends of Pathways also works with Jackson Hole Community Pathways and Teton County Parks and Recreation to ensure pathways are swept and safe.
Trail Report, July 20, 2011
Greater Snow King Area/Munger Mountain Area/Teton Pass Area
Arrow to Phillips is rideable and 99% snow free, but do be aware of the trench near the creek crossing at the bottom where the high water caused damage. Blacks is now snow free; the Ridge Trail is riding well as are the lower downhill trails. The Jumps Trail reroute is finished and the Teton Freedom Riders - as part of the JH Trails Project - are working on the bottom part of the Fuzzy Bunny Trail, which is closed halfway down during construction.
Trails Projects, Summer 2011:
Pathways Report, July 20, 2011
Pathways will be installing a “pathway travel lane” for users on the North 89 pathway south of the Fish Hatchery Road. There is an unfinished section of pathway just south of the Fish Hatchery, and pathway users are required to use the highway shoulder between the completed sections. Traffic delineators will be placed on the shoulder to separate pathway users from motor vehicles. The “travel lane” will be in place until the pathway is completed later this summer.
Please let us know if there are any concerns or questions about maintenance and safety conditions on pathways and trails at stewardship@friendsofpathways.org, or call 733-4534.
Harlan and the team have been hard at work rebuilding the Powerline jumps. Although it’s not finished it is worth going over to see the progress and to check out “history” in the remaking. This means both a better and safer trail for all riding abilities.
Currently the Candy Land Connector is too muddy to ride due to run off; please stay off until the high snow melts away. Jimmy’s Mom is in good shape but be cautious of up hill traffic on Old Pass Road while descending.
The progression of our trails system is due in large part to our collaboration with the USFS. If you’d like, share your thoughts on our Teton Pass trail system with those directly involved by sending an email to either Linda or Dale:
See you at the July Dig Day on Sunday the 10th!
Trail Report, June 13, 2011
Greater Snow King Area/Munger Mountain Area/Teton Pass Area
Greater Snow King Area
FOP crews dug drainage on Putt-Putt and worked on some new seeping areas. They worked on re-benching some sections of Josie’s and re-vegging braided sections of the trail. They also finished the Cache Creek Sidewalk extension begun on National Trails Day, which connects the Sidewalk to bridge 3, allowing people to use the Sidewalk to bypass the Hagen stairs.
Trails on Snow King that are free of snow include Putt-Putt, Cache Creek Sidewalk, Hagen River, Hagen 2 Track, High Hagen, Sink or Swim, KC, Linda’s, Flat Creek, and Josie’s Ridge.
Ferrins Trail – the trail to the meadows is open and provides a great out and back. The entire trail should be open by this weekend.
West Game – This canyon may be open by the coming weekend, but there is a good bit of water everywhere.
Cache Creek Trail above Hagen and Putt-Putt – This is still a mess, but by the weekend we should be looking to be clear of snow to Bridge 6 (Cache/Game Bridge).
GSKA Notes:
You will notice bridges in Cache Creek are now numbered just in case they get washed away. If you see a bridge floating away, please let FOP or the USFS know!
The Cache/Game mountain bike race may be moved back a few weeks (it was scheduled for June 22). Please check with Teton County Parks and Rec for more info.